1. High-risk situations
Do not
start up or shut down equipment or installations without using the appropriate
written operating procedure.
Any situation where the risk level is
temporarily increased is reported. Induced risks are identified and analyzed and
compensatory measures are implemented.
2. Traffic: Machine/vehicle/cyclist/pedestrians
Do not
exceed the speed limits.
Traffic rules apply inside and
outside sites.
3. Body mechanics and tools
Do not
carry out work if you do not have the right tools for the job and the
environment.
Adopting an inappropriate posture
when handling objects or using tools can cause physical harm.
4. Protective equipment
Do not
access installations and perform work without wearing general or task-specific
personal protective equipment (PPE).
Collective protection is preferred.
Individual protection completes preventive measures already taken.
5. Work permits
Do not
perform work without a valid work permit.
Any work performed on site requires a
permit.
6. Lifting
Do not walk
under a load while lifting is taking place.
For any work involving a crane, hoist
or other mechanical system, a preliminary risk analysis is required. Equipment
must be in good condition. Personnel must be qualified and access to the area
must be restricted.
7. Work on powered systems
Do not
perform work without checking that the power and product source supply has been
rendered inoperative.
Some works require the energy to be
safely discharge or the equipment to be purged and vented. In such cases a
lockout system is set up to isolate the energy or product according to a
specific method.
8. Confined spaces
Do not
enter a confined space until isolation has been verified and the atmosphere
checked.
Do not enter a confined space
(container, tank, well, etc…) without supervision and only after the atmosphere
and isolation have been checked.
9. Excavation work
Do not
perform excavation work without a valid work permit comprising a map of all
underground hazards.
Manual or mechanical excavation work,
including dragging rivers and seabeds, can only start after a risk analysis has
been performed to identify all hazards in the zone and related precautions have
been taken.
10. Working at heights
Do not work
at heights without a safety harness when there is no collective protective
equipment.
Work at heights is performed on fixed
or mobile platforms with a guardrail designed for the task at hand.
Work on rooftops (buildings,
reservoirs) is performed only after the roof's solidity has been checked and
appropriate protection has been set up.
Ladders are a means of access only;
their use must remain exceptional.
11. Change management
Do not make
any technical or organizational changes without prior authorization.
Any changes in technique or organization
must be the subject of a risk analysis.
12. Simultaneous operations or co-activities
Do not
perform simultaneous operations or co-activities without a prior visit.
All work or operations inside a unit
in operation can increase risk levels. Interferences due to simultaneous
operations or joint-activities must be identified and controlled.
No comments: